Crag Walk and Naze Heritage Projects are presented to TDC Management Board & Cabinet

Cabinet approve project

Project Appraisal Report (PAR) to be completed by Royal Haskoning Consultants – required to accompany Crag Walk planning application

PAR accepted October 2009

Planning application approved

Expected early 2010

Progress fundraising – apply for grants including Heritage Lottery

Several applications being submitted

Detailed Crag Walk design completed

 

Planning permission for Crag Walk submitted and decision

 

Crag Walk advertised under Coastal Protection Act

 

Detailed contract documents prepared for Crag Walk

 

Responses from funders

 

Anticipated Construction of Crag Walk

2010

 

 

Banner Photo (top of page)

View of Naze cliffs and Naze tower - Photograph by Nigel Pepper

 

info@nazeprotectionsociety.org.uk

Tel: 01255 676868

Registered Charity No: 1064011

 
NPS Logo      EWT Logo      Naze Tower Logo      TDC Logo